49, Simandhar Royale, Chembur
by Simandhar Homes LLP · Chembur, Mumbai 400071 · Map
- Launched
- Oct 20233 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 89 of 11379% · 36 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale89 booked out of 113 units
Rehab36 units for existing members
Land-owner share37 units, not for sale
Total 186 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 123
- 2 BHK
- 62
- 3 BHK
- 1
- Total units
- 186
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 113
- Rehab units
- 36
- Land-owner share (not for sale)
- 37
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 40% | 89 | |
| 100% | 100% | 0% | 80 | |
| 100% | 100% | 0% | 61 | |
| 100% | 15% | 0% | 11 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400071
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2027 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 79% | 54% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Arham Mourya, Chembur
- Poddar Harmony, Chembur
- Queens Avenue, Chembur
- Roha Eva Aria, Chembur
- Subhash Nagar Navrang Chs Adityaraj Supreme, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Arham Mourya | November 2023 | December 2026 | 100% | 89 units booked out of 93 units for sale |
| Poddar Harmony | November 2023 | June 2028 | 100% | 60 units booked out of 112 units for sale |
| Queens Avenue | January 2024 | December 2027 | 0% | 145 units booked out of 161 units for sale |
| Roha Eva Aria | January 2024 | December 2027 | 0% | 69 units booked out of 154 units for sale |
| Subhash Nagar Navrang Chs Adityaraj Supreme | June 2023 | December 2026 | 100% | 74 units booked out of total 137 units |
About this project
49, Simandhar Royale by Simandhar Homes LLP is a 186-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in October 2023 with possession due in December 2026. 89 units booked out of 113 units for sale. The concrete structure (RCC) is complete.
Read full summary
49, Simandhar Royale is a MHADA-sanctioned project by Simandhar Homes LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800053382. It was launched in October 2023. It has 186 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 186 units, 113 are for sale, 36 are rehab units for existing members and 37 are the land-owner's share, not for sale.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.
89 units booked out of 113 units for sale (79%). Since the July 2026 update, 9 more units have been booked.