Queens Avenue, Chembur

by V Laxmi Estate Developers Private Limited · Chembur, Mumbai 400071 · Map

Launched
Jan 20243 yrs 11 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
145 of 16190% · 37 rehab units
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale145 booked out of 161 units

Rehab37 units for existing members

Total 198 units. Rehab units are not for sale.

Project facts

1 BHK
93
2 BHK
92
Other units
13
Total units
198
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
161
Rehab units
37

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation30%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 30%Dec 2025: Excavation 30%Jul 2026: Excavation 30%Oct 2026: Excavation 30%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 30%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
30%0%0%145
30%0%0%–
30%0%0%–
30%0%0%14

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 90–400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Jul 2027
Concrete structure (RCC)0%100%
Units booked (free sale)90%70%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Queens Avenue by V Laxmi Estate Developers Private Limited is a 198-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in January 2024 with possession due in December 2027. 145 units booked out of 161 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Queens Avenue is a MHADA-sanctioned project by V Laxmi Estate Developers Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51800054458. It was launched in January 2024. It has 198 units in 2 buildings: 185 homes (1 and 2 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 198 units, 161 are for sale and 37 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation 30% complete, structure (RCC) not started, final finishes not started.

145 units booked out of 161 units for sale (90%).