Arham Mourya, Chembur

Ready to move

by Mahavir Millennium LLP · Chembur, Mumbai 400071 · Map

Launched
Nov 20233 yrs 1 mth promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
89 of 9396% · 65 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale89 booked out of 93 units

Rehab65 units for existing members

Total 158 units. Rehab units are not for sale.

Project facts

1 BHK
24
2 BHK
108
3 BHK
21
Other units
5
Total units
158
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
93
Rehab units
65

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 74%Dec 2025: Concrete structure (RCC) 74%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 90%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%89
100%100%90%82
100%74%0%–
100%74%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2026Jul 2027
Concrete structure (RCC)100%100%
Units booked (free sale)96%74%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Arham Mourya by Mahavir Millennium LLP is a 158-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in November 2023 with possession due in December 2026. 89 units booked out of 93 units for sale. The concrete structure (RCC) is complete.

Read full summary

Arham Mourya is a BMC-sanctioned project by Mahavir Millennium LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800053514. It was launched in November 2023. It has 158 units in 2 buildings: 153 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 158 units, 93 are for sale and 65 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

89 units booked out of 93 units for sale (96%). Since the July 2026 update, 7 more units have been booked.