Rang Rekha, Dahisar
by Ashapura Infratech · Dahisar, Mumbai 400068 · Map
- Launched
- Feb 20243 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 66%Mid-construction
- Booked (free sale)
- 76 of 76100% · 40 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale76 booked out of 76 units
Rehab40 units for existing members
Total 116 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 92
- 3 BHK
- 4
- Total units
- 116
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 76
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 66% | 0% | 76 | |
| 100% | 66% | 0% | – | |
| 100% | 66% | 0% | – | |
| 100% | 42% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400068
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2026 |
| Concrete structure (RCC) | 66% | 98% |
| Units booked (free sale) | 100% | 66% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Ashtha Sharon Dahisar West, Dahisar
- Sahakar Vista, Dahisar
- Modirealty Acacia, Dahisar
- Nageshwar Sra Chs, Dahisar
- Krishna Kripa, Dahisar
- Raghukul Chsl, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashtha Sharon Dahisar West | April 2024 | December 2026 | 96% | 0 units booked out of 28 units for sale |
| Sahakar Vista | November 2023 | July 2026 | 100% | 113 units booked out of total 117 units |
| Modirealty Acacia | May 2024 | March 2028 | 100% | 61 units booked out of 96 units for sale |
| Nageshwar Sra Chs | November 2023 | December 2026 | 52% | 17 units booked out of 36 units for sale |
| Krishna Kripa | October 2023 | August 2026 | 100% | 26 units booked out of 38 units for sale |
| Raghukul Chsl | July 2024 | December 2029 | 85% | 95 units booked out of 121 units for sale |
About this project
Rang Rekha by Ashapura Infratech is a 116-unit MHADA-sanctioned project in Dahisar, Mumbai 400068, launched in February 2024 with possession due in December 2027. 76 units booked out of 76 units for sale. The concrete structure (RCC) is 66% complete.
Read full summary
Rang Rekha is a MHADA-sanctioned project by Ashapura Infratech in Dahisar, Mumbai 400068, registered with MahaRERA as P51800054737. It was launched in February 2024. It has 116 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 116 units, 76 are for sale and 40 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 66% complete, final finishes not started.
76 units booked out of 76 units for sale (100%).