Ananta, Mulund West

by K Ajmera Developers · Mulund West, Mumbai 400080 · Map

Launched
Nov 20231 yr 9 mths originally promised
Possession (MahaRERA)
Aug 2026Extended by 1 yr
Concrete structure
98%Mid-construction
Booked (free sale)
24 of 5246% · 27 rehab units
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale24 booked out of 52 units

Rehab27 units for existing members

Total 79 units. Rehab units are not for sale.

Project facts

1 BHK
17
2 BHK
39
3 BHK
20
4 BHK
1
Other units
2
Total units
79
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
52
Rehab units
27

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)98%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 98%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 98%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%98%50%24
100%80%0%16
100%80%0%17
100%50%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths3 yrs 4 mths
Possession date extendedBy 1 yr1 of 6
Possession date (MahaRERA)Aug 2026May 2027
Concrete structure (RCC)98%5%
Units booked (free sale)46%35%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ananta by K Ajmera Developers is a 79-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in November 2023 with possession due in August 2026. 24 units booked out of 52 units for sale. The concrete structure (RCC) is 98% complete.

Read full summary

Ananta is a BMC-sanctioned project by K Ajmera Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800053780. It was launched in November 2023. It has 79 units in 1 building: 77 homes (1, 2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 79 units, 52 are for sale and 27 are rehab units for existing members.

Possession was due in August 2026, after an extension of 1 year from the original August 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 98% complete, final finishes 50% complete.

24 units booked out of 52 units for sale (46%). Since the July 2026 update, 8 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 98%.