Divya Jyot Rewa Estate, Mulund West

by Divya Jyot Projects LLP · Mulund West, Mumbai 400080 · Map

Launched
Jan 20242 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2028Extended by 2 yrs
Concrete structure
56%Mid-construction
Booked (free sale)
16 of 4635% · 47 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale16 booked out of 46 units

Rehab47 units for existing members

Total 93 units. Rehab units are not for sale.

Project facts

1 RK
20
1 BHK
20
2 BHK
29
Other units
24
Total units
93
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
46
Rehab units
47

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)56%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 56%Oct 2026: Concrete structure (RCC) 56%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 18%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 56%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%56%20%16
100%56%18%16
100%0%0%11
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs
Possession date extendedBy 2 yrs2 of 6
Possession date (MahaRERA)Dec 2028Feb 2027
Concrete structure (RCC)56%48%
Units booked (free sale)35%44%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Divya Jyot Rewa Estate by Divya Jyot Projects LLP is a 93-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in January 2024 with possession due in December 2028. 16 units booked out of 46 units for sale. The concrete structure (RCC) is 56% complete.

Read full summary

Divya Jyot Rewa Estate is a BMC-sanctioned project by Divya Jyot Projects LLP in Mulund West, Mumbai 400080, registered with MahaRERA as P51800054575. It was launched in January 2024. It has 93 units in 1 building: 69 homes (1 RK, 1 BHK and 2 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 93 units, 46 are for sale and 47 are rehab units for existing members.

Its registered possession date is December 2028, extended by 2 years from the original December 2026. Construction: excavation complete, structure (RCC) 56% complete, final finishes 20% complete.

16 units booked out of 46 units for sale (35%).