Ratnadeep, Mulund West

by Ashapura Developers · Mulund West, Mumbai 400080 · Map

Launched
Dec 20233 yrs 6 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
55%Mid-construction
Booked (free sale)
51 of 6480%
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale51 booked out of 64 units

Land-owner share15 units, not for sale

Total 79 units. Land-owner units are not for sale.

Project facts

1 BHK
20
2 BHK
44
3 BHK
10
Other units
5
Total units
79
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
64
Land-owner share (not for sale)
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)55%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 83%Dec 2025: Concrete structure (RCC) 83%Jul 2026: Concrete structure (RCC) 83%Oct 2026: Concrete structure (RCC) 55%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 98%Excavation 100%Final finishes 98%Concrete structure (RCC) 55%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%55%98%51
100%83%0%–
100%83%0%–
100%83%0%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths2 yrs 10 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Jun 2027Jan 2027
Concrete structure (RCC)55%48%
Units booked (free sale)80%40%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ratnadeep by Ashapura Developers is a 79-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in December 2023 with possession due in June 2027. 51 units booked out of 64 units for sale. The concrete structure (RCC) is 55% complete.

Read full summary

Ratnadeep is a BMC-sanctioned project by Ashapura Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800053957. It was launched in December 2023. It has 79 units in 2 buildings: 74 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 79 units, 64 are for sale and 15 are the land-owner's share, not for sale.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes 98% complete.

51 units booked out of 64 units for sale (80%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 83% to 55%.