Skip to main content

Ghanwat Accord, Malad East

by Ghanwat Developers Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
50 of 5985% · 9 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale50 booked out of 59 units

Rehab9 units for existing members

Total 68 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
42
Other units
20
Total units
68
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
59
Rehab units
9
Reserved units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 55%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 90%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%70%50
100%80%55%47
100%60%0%31
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400097

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths2 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027Sep 2027
Concrete structure (RCC)90%100%
Units booked (free sale)85%47%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ghanwat Accord by Ghanwat Developers Pvt Ltd is a 68-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in June 2024 with possession due in December 2027. 50 units booked out of 59 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Ghanwat Accord is a BMC-sanctioned project by Ghanwat Developers Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800066476. It was launched in June 2024. It has 68 units in 1 building: 48 homes (1 and 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 68 units, 59 are for sale and 9 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 70% complete.

50 units booked out of 59 units for sale (85%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 90%.