Skip to main content

Pratap Liberty One, Malad West

by Downtown Lifespaces LLP · Malad West, Mumbai 400064 · Map

Launched
Jan 20243 yrs 11 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
39%Mid-construction
Booked (free sale)
20 of 3951% · 40 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 39 units

Rehab40 units for existing members

Total 79 units. Rehab units are not for sale.

Project facts

1 BHK
38
2 BHK
36
3 BHK
1
Other units
4
Total units
79
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
39
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)39%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 39%Jul 2026: Concrete structure (RCC) 39%Oct 2026: Concrete structure (RCC) 39%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 39%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%39%0%20
100%39%0%–
100%39%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths3 yrs 4 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Dec 2027Jul 2027
Concrete structure (RCC)39%100%
Units booked (free sale)51%51%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pratap Liberty One by Downtown Lifespaces LLP is a 79-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in January 2024 with possession due in December 2027. 20 units booked out of 39 units for sale. The concrete structure (RCC) is 39% complete.

Read full summary

Pratap Liberty One is a BMC-sanctioned project by Downtown Lifespaces LLP in Malad West, Mumbai 400064, registered with MahaRERA as P51800054465. It was launched in January 2024. It has 79 units in 1 building: 75 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 79 units, 39 are for sale and 40 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 39% complete, final finishes not started.

20 units booked out of 39 units for sale (51%).