Advent Deepak, Malad West

by Advent Developers Private Limited · Malad West, Mumbai 400064 · Map

Launched
Feb 20241 yr 10 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 2 yrs
Concrete structure
80%Mid-construction
Booked (free sale)
5 of 4810% · 26 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 48 units

Rehab26 units for existing members

Total 74 units. Rehab units are not for sale.

Project facts

1 BHK
38
2 BHK
9
3 BHK
27
Total units
74
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
48
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 65%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%5
100%65%0%1
100%50%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 10 mths4 yrs 2 mths
Possession date extendedBy 2 yrs0 of 6
Possession date (MahaRERA)Dec 2027Mar 2028
Concrete structure (RCC)80%34%
Units booked (free sale)10%48%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Advent Deepak by Advent Developers Private Limited is a 74-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in February 2024 with possession due in December 2027. 5 units booked out of 48 units for sale. The concrete structure (RCC) is 80% complete.

Read full summary

Advent Deepak is a BMC-sanctioned project by Advent Developers Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as P51800054861. It was launched in February 2024. It has 74 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 74 units, 48 are for sale and 26 are rehab units for existing members.

Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.

5 units booked out of 48 units for sale (10%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 65% to 80%.