by Shreeji Construction · Malad West, Mumbai 400064 · Map

Launched
Jan 20244 yrs 5 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
30%Mid-construction
Booked (free sale)
25 of 5545% · 26 rehab units
Buildings
10.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 55 units

Rehab26 units for existing members

Total 81 units. Rehab units are not for sale.

Project facts

3 BHK
65
Other units
16
Total units
81
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
1
Free-sale units
55
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)30%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 12%Oct 2026: Concrete structure (RCC) 30%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 30%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%30%0%25
100%12%0%14
100%0%0%8
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 5 mths3 yrs
Possession date extendedNo2 of 6
Possession date (MahaRERA)Jun 2028Feb 2027
Concrete structure (RCC)30%82%
Units booked (free sale)45%61%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shreeji Eternity Wing - D by Shreeji Construction is an 81-unit SRA-sanctioned project in Malad West, Mumbai 400064, launched in January 2024 with possession due in June 2028. 25 units booked out of 55 units for sale. The concrete structure (RCC) is 30% complete.

Read full summary

Shreeji Eternity Wing - D is an SRA-sanctioned project by Shreeji Construction in Malad West, Mumbai 400064, registered with MahaRERA as P51800054233. It was launched in January 2024. It has 81 units in 1 building: 65 homes (3 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 81 units, 55 are for sale and 26 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.

25 units booked out of 55 units for sale (45%). Since the July 2026 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 12% to 30%.