Ramkrishna, Vile Parle East

by M/S. Suryashobha Homes LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Feb 20241 yr 1 mth originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr 9 mths
Concrete structure
100%Nearing possession
Booked (free sale)
6 of 1638% · 22 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 16 units

Rehab22 units for existing members

Total 38 units. Rehab units are not for sale.

Project facts

1 RK
9
1 BHK
7
2 BHK
20
3 BHK
2
Total units
38
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 30%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 30%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%6
100%90%30%2
100%40%0%2
30%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 1 mth3 yrs 8 mths
Possession date extendedBy 1 yr 9 mths1 of 6
Possession date (MahaRERA)Dec 2026Mar 2028
Concrete structure (RCC)100%80%
Units booked (free sale)38%56%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ramkrishna by M/S. Suryashobha Homes LLP is a 38-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in February 2024 with possession due in December 2026. 6 units booked out of 16 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ramkrishna is a BMC-sanctioned project by M/S. Suryashobha Homes LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800054622. It was launched in February 2024. It has 38 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 16 are for sale and 22 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year 9 months from the original March 2025. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

6 units booked out of 16 units for sale (38%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 90% to 100%.