by Anusri Enterprises LLP · Vile Parle East, Mumbai 400057 · Map

Launched
Jan 20242 yrs 7 mths promised
Possession (MahaRERA)
Aug 2026Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
10 of 1377% · 15 rehab units
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 13 units

Rehab15 units for existing members

Total 28 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
6
2 BHK
13
3 BHK
2
4 BHK
5
Total units
28
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 55%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%10
100%60%0%10
100%55%0%7
100%50%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400057

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400057
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths3 yrs 6 mths
Possession date extendedNo3 of 6
Possession date (MahaRERA)Aug 2026Jun 2028
Concrete structure (RCC)60%100%
Units booked (free sale)77%63%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sandeep Ankur Residency by Anusri Enterprises LLP is a 28-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in January 2024 with possession due in August 2026. 10 units booked out of 13 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Sandeep Ankur Residency is a BMC-sanctioned project by Anusri Enterprises LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800054360. It was launched in January 2024. It has 28 units in 2 buildings, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 13 are for sale and 15 are rehab units for existing members.

Possession was due in August 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

10 units booked out of 13 units for sale (77%).