Zodiac Anjaneshwar, Vile Parle East
by Zodiac Ventures Limited · Vile Parle East, Mumbai 400057 · Map
- Launched
- Jan 20241 yr 5 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 2 yrs 6 mths
- Concrete structure
- 56%Mid-construction
- Booked (free sale)
- 5 of 956% · 21 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 9 units
Rehab21 units for existing members
Total 30 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 16
- 2 BHK
- 11
- Total units
- 30
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 56% | 0% | 5 | |
| 100% | 56% | 0% | 5 | |
| 100% | 56% | 0% | 5 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 5 mths | 3 yrs 9 mths |
| Possession date extended | By 2 yrs 6 mths | 2 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Jan 2028 |
| Concrete structure (RCC) | 56% | 100% |
| Units booked (free sale) | 56% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Sandeep Ankur Residency, Vile Parle East
- Atharv Casa, Vile Parle East
- Vibha Vasu, Vile Parle East
- Ramkrishna, Vile Parle East
- Atharv Om Chandramilan, Vile Parle East
- Ganesh Chhaya Co-Operative Housing Society Ltd, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sandeep Ankur Residency | January 2024 | August 2026 | 60% | 10 units booked out of 13 units for sale |
| Atharv Casa | January 2024 | December 2028 | 100% | 12 units booked out of 17 units for sale |
| Vibha Vasu | December 2023 | February 2027 | 100% | 16 units booked out of 16 units for sale |
| Ramkrishna | February 2024 | December 2026 | 100% | 6 units booked out of 16 units for sale |
| Atharv Om Chandramilan | December 2023 | December 2028 | 100% | 10 units booked out of 10 units for sale |
| Ganesh Chhaya Co-Operative Housing Society Ltd | December 2023 | December 2028 | 100% | 7 units booked out of 21 units for sale |
About this project
Zodiac Anjaneshwar by Zodiac Ventures Limited is a 30-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in January 2024 with possession due in December 2027. 5 units booked out of 9 units for sale. The concrete structure (RCC) is 56% complete.
Read full summary
Zodiac Anjaneshwar is a BMC-sanctioned project by Zodiac Ventures Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800054548. It was launched in January 2024. It has 30 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 9 are for sale and 21 are rehab units for existing members.
Its registered possession date is December 2027, extended by 2 years 6 months from the original June 2025. Construction: excavation complete, structure (RCC) 56% complete, final finishes not started.
5 units booked out of 9 units for sale (56%).