I Space Urban Vista, Borivali West

by Rt Housing Private Limited & Shree Shantee Developers · Borivali West, Mumbai 400092 · Map

Launched
Feb 20243 yrs 6 mths originally promised
Possession (MahaRERA)
Jun 2029Extended by 1 yr 10 mths
Concrete structure
7%Mid-construction
Booked
28 of 7239% · 25 in Jul 2026
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
33
2 BHK
16
Other units
23
Total units
72
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Reserved units
25

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)7%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 50%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 2%Oct 2026: Concrete structure (RCC) 7%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 7%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%7%0%28
50%2%0%25
100%0%0%25
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs 9 mths
Possession date extendedBy 1 yr 10 mths2 of 6
Possession date (MahaRERA)Jun 2029Dec 2027
Concrete structure (RCC)7%100%
Units booked39%57%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

I Space Urban Vista by Rt Housing Private Limited & Shree Shantee Developers is a 72-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in February 2024 with possession due in June 2029. 28 units booked out of total 72 units. The concrete structure (RCC) is 7% complete.

Read full summary

I Space Urban Vista is an SRA-sanctioned project by Rt Housing Private Limited & Shree Shantee Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800054640. It was launched in February 2024. It has 72 units in 2 buildings: 49 homes (1 and 2 BHK) and 23 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, extended by 1 year 10 months from the original August 2027. Construction: excavation 50% complete, structure (RCC) 7% complete, final finishes not started.

28 units booked out of total 72 units (39%). Since the July 2026 update, 3 more units have been booked, the reported concrete structure (RCC) has gone from 2% to 7% and the possession date has moved from August 2027 to June 2029.