Ganapati Baug CHSL, Borivali West
by Nitai Gaur Enterprises · Borivali West, Mumbai 400092 · Map
- Launched
- Feb 20243 yrs 11 mths promised
- Possession (MahaRERA)
- Jan 2028Not extended
- Concrete structure
- 14%Mid-construction
- Booked (free sale)
- 20 of 3951% · 63 rehab units
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale20 booked out of 39 units
Rehab63 units for existing members
Total 102 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 2
- 2 BHK
- 46
- 3 BHK
- 20
- 4 BHK
- 1
- 5+ BHK
- 1
- Other units
- 32
- Total units
- 102
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 39
- Rehab units
- 63
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 14% | 0% | 20 | |
| 100% | 94% | 0% | 9 | |
| 100% | 50% | 0% | 5 | |
| 100% | 11% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 11 mths | 3 yrs 7 mths |
| Possession date extended | No | 4 of 6 |
| Possession date (MahaRERA) | Jan 2028 | Dec 2027 |
| Concrete structure (RCC) | 14% | 100% |
| Units booked (free sale) | 51% | 51% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- I Space Urban Vista, Borivali West
- Anjani Shikhar, Borivali West
- Om Shri Jagannath Chsl, Borivali West
- Om Amar Shakti, Borivali West
- Shree Radhe Shyam Heights, Borivali West
- Palash, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| I Space Urban Vista | February 2024 | June 2029 | 7% | 28 units booked out of total 72 units |
| Anjani Shikhar | February 2024 | December 2027 | 100% | 6 units booked out of total 39 units |
| Om Shri Jagannath Chsl | January 2024 | December 2026 | 100% | 14 units booked out of 22 units for sale |
| Om Amar Shakti | April 2024 | April 2028 | 76% | 7 units booked out of 35 units for sale |
| Shree Radhe Shyam Heights | April 2024 | December 2027 | 100% | 14 units booked out of 22 units for sale |
| Palash | November 2023 | December 2026 | 100% | 32 units booked out of 38 units for sale |
About this project
Ganapati Baug CHSL by Nitai Gaur Enterprises is a 102-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in February 2024 with possession due in January 2028. 20 units booked out of 39 units for sale. The concrete structure (RCC) is 14% complete.
Read full summary
Ganapati Baug CHSL is a BMC-sanctioned project by Nitai Gaur Enterprises in Borivali West, Mumbai 400092, registered with MahaRERA as P51800055078. It was launched in February 2024. It has 102 units in 2 buildings: 70 homes (1, 2, 3, 4 and 5+ BHK) and 32 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 102 units, 39 are for sale and 63 are rehab units for existing members.
Its registered possession date is January 2028, unchanged since launch. Construction: excavation 50% complete, structure (RCC) 14% complete, final finishes not started.
20 units booked out of 39 units for sale (51%). Since the July 2026 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 94% to 14%.