Om Amar Shakti, Borivali West

by Shree Shakti Realty · Borivali West, Mumbai 400092 · Map

Launched
Apr 20243 yrs 8 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 4 mths
Concrete structure
76%Mid-construction
Booked (free sale)
7 of 3520% · 26 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 35 units

Rehab26 units for existing members

Total 61 units. Rehab units are not for sale.

Project facts

2 BHK
32
3 BHK
16
Other units
13
Total units
61
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
35
Rehab units
26

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)76%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 0%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 76%Dec 2024: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 76%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%76%0%7
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 9 mths
Possession date extendedBy 4 mths1 of 6
Possession date (MahaRERA)Apr 2028Jan 2028
Concrete structure (RCC)76%100%
Units booked (free sale)20%35%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Om Amar Shakti by Shree Shakti Realty is a 61-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in April 2024 with possession due in April 2028. 7 units booked out of 35 units for sale. The concrete structure (RCC) is 76% complete.

Read full summary

Om Amar Shakti is a BMC-sanctioned project by Shree Shakti Realty in Borivali West, Mumbai 400092, registered with MahaRERA as P51800055675. It was launched in April 2024. It has 61 units in 1 building: 48 homes (2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 61 units, 35 are for sale and 26 are rehab units for existing members.

Its registered possession date is April 2028, extended by 4 months from the original December 2027. Construction: excavation complete, structure (RCC) 76% complete, final finishes not started.

7 units booked out of 35 units for sale (20%). Since the December 2024 update, 7 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 76% and the possession date has moved from December 2027 to April 2028.