Dedhia Avenue, Mulund West

by Satish Chimanlal Dedhia · Mulund West, Mumbai 400080 · Map

Launched
Feb 20243 yrs 3 mths promised
Possession (MahaRERA)
May 2027Not extended
Concrete structure
25%Mid-construction
Booked (free sale)
13 of 3142% · 30 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 31 units

Rehab30 units for existing members

Land-owner share3 units, not for sale

Total 64 units. Rehab and land-owner units are not for sale.

Project facts

2 BHK
28
3 BHK
10
4 BHK
1
Other units
25
Total units
64
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
31
Rehab units
30
Land-owner share (not for sale)
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)25%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 25%Dec 2025: Concrete structure (RCC) 25%Jul 2026: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 25%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 25%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%25%0%13
100%25%0%–
100%25%0%–
100%25%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths2 yrs 10 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)May 2027Dec 2026
Concrete structure (RCC)25%58%
Units booked (free sale)42%37%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Dedhia Avenue by Satish Chimanlal Dedhia is a 64-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in February 2024 with possession due in May 2027. 13 units booked out of 31 units for sale. The concrete structure (RCC) is 25% complete.

Read full summary

Dedhia Avenue is a BMC-sanctioned project by Satish Chimanlal Dedhia in Mulund West, Mumbai 400080, registered with MahaRERA as P51800054991. It was launched in February 2024. It has 64 units in 1 building: 39 homes (2, 3 and 4 BHK) and 25 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 64 units, 31 are for sale, 30 are rehab units for existing members and 3 are the land-owner's share, not for sale.

Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.

13 units booked out of 31 units for sale (42%).