Om Kailash Ganga CHS LTD, Mulund West
by R K Developers · Mulund West, Mumbai 400080 · Map
- Launched
- Feb 20243 yrs 8 mths promised
- Possession (MahaRERA)
- Oct 2027Not extended
- Concrete structure
- 40%Mid-construction
- Booked (free sale)
- 3 of 2711% · 33 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 27 units
Rehab33 units for existing members
Total 60 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 15
- 3 BHK
- 45
- Total units
- 60
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 27
- Rehab units
- 33
- Reserved units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 40% | 0% | 3 | |
| 100% | 30% | 0% | 3 | |
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 8 mths | 3 yrs 1 mth |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Oct 2027 | May 2027 |
| Concrete structure (RCC) | 40% | 40% |
| Units booked (free sale) | 11% | 61% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Dedhia Avenue, Mulund West
- Aai Satidevi Paradise, Mulund West
- Divya Jyot Rewa Estate, Mulund West
- Kdo Chsl, Mulund West
- Ratnadeep, Mulund West
- Advani Skyview, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dedhia Avenue | February 2024 | May 2027 | 25% | 13 units booked out of 31 units for sale |
| Aai Satidevi Paradise | February 2024 | September 2026 | 98% | 103 units booked out of total 128 units |
| Divya Jyot Rewa Estate | January 2024 | December 2028 | 56% | 16 units booked out of 46 units for sale |
| Kdo Chsl | January 2024 | November 2026 | 0% | 9 units booked out of total 75 units |
| Ratnadeep | December 2023 | June 2027 | 55% | 51 units booked out of 64 units for sale |
| Advani Skyview | April 2024 | December 2027 | 0% | 42 units booked out of 51 units for sale |
About this project
Om Kailash Ganga CHS LTD by R K Developers is a 60-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in February 2024 with possession due in October 2027. 3 units booked out of 27 units for sale. The concrete structure (RCC) is 40% complete.
Read full summary
Om Kailash Ganga CHS LTD is a BMC-sanctioned project by R K Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800054928. It was launched in February 2024. It has 60 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 60 units, 27 are for sale and 33 are rehab units for existing members.
Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 40% complete, final finishes not started.
3 units booked out of 27 units for sale (11%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 30% to 40%.