Skip to main content

Rishab Laxmi, Malad West

by Aditi Developers · Malad West, Mumbai 400064 · Map

Launched
Feb 20242 yrs 10 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
20%Mid-construction
Booked (free sale)
6 of 967% · 24 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 9 units

Rehab24 units for existing members

Total 33 units. Rehab units are not for sale.

Project facts

1 BHK
13
2 BHK
18
Other units
2
Total units
33
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)20%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 20%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 20%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%20%0%6
100%60%0%6
100%50%0%5
100%10%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths2 yrs
Possession date extendedNo3 of 6
Possession date (MahaRERA)Dec 2026Jan 2027
Concrete structure (RCC)20%82%
Units booked (free sale)67%51%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rishab Laxmi by Aditi Developers is a 33-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in February 2024 with possession due in December 2026. 6 units booked out of 9 units for sale. The concrete structure (RCC) is 20% complete.

Read full summary

Rishab Laxmi is a BMC-sanctioned project by Aditi Developers in Malad West, Mumbai 400064, registered with MahaRERA as P51800055091. It was launched in February 2024. It has 33 units in 1 building: 31 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 9 are for sale and 24 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.

6 units booked out of 9 units for sale (67%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 60% to 20%.