- Launched
- Apr 20241 yr 8 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 9 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 1 of 166% · 11 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 16 units
Rehab11 units for existing members
Total 27 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 19
- 3 BHK
- 8
- Total units
- 27
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 16
- Rehab units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 1 | |
| 100% | 100% | 2% | 1 | |
| 0% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400064
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 8 mths | 2 yrs 11 mths |
| Possession date extended | By 9 mths | 0 of 6 |
| Possession date (MahaRERA) | Sep 2026 | Apr 2027 |
| Concrete structure (RCC) | 100% | 64% |
| Units booked (free sale) | 6% | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Sagar Sarita Co-operative Housing Society LTD, Malad West
- Shiv Palace, Malad West
- Rishab Laxmi, Malad West
- Sadguru Avighna, Malad West
- Rajgopal Building, Malad West
- Milan Mandir Nx, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sagar Sarita Co-operative Housing Society LTD | April 2024 | December 2028 | 15% | 40 units booked out of total 57 units |
| Shiv Palace | May 2024 | May 2027 | 100% | 6 units booked out of 6 units for sale |
| Rishab Laxmi | February 2024 | December 2026 | 20% | 6 units booked out of 9 units for sale |
| Sadguru Avighna | June 2024 | December 2027 | 100% | 27 units booked out of total 43 units |
| Rajgopal Building | June 2024 | September 2026 | 35% | 0 units booked out of 2 units for sale |
| Milan Mandir Nx | June 2024 | March 2027 | 93% | 10 units booked out of 18 units for sale |
About this project
Shree Hari Krupa by Mamtora Foundation is a 27-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in April 2024; its MahaRERA registration has lapsed. 1 unit booked out of 16 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shree Hari Krupa is a BMC-sanctioned project by Mamtora Foundation in Malad West, Mumbai 400064, registered with MahaRERA as P51800055568. It was launched in April 2024. It has 27 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 27 units, 16 are for sale and 11 are rehab units for existing members.
Possession was due in September 2026, after an extension of 9 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
1 unit booked out of 16 units for sale (6%).