Mesacon Crown, Andheri West

by Mesacon Spaces LLP · Andheri West, Mumbai 400058 · Map

Launched
Apr 20243 yrs 2 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
37 of 4092% · 47 rehab units
Buildings
20.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale37 booked out of 40 units

Rehab47 units for existing members

Total 87 units. Rehab units are not for sale.

Project facts

1 BHK
1
2 BHK
58
3 BHK
25
4 BHK
1
Other units
2
Total units
87
Buildings
2
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
40
Rehab units
47

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services18%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 18%Excavation 100%Concrete structure (RCC) 100%Final finishes 18%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%18%37
100%100%0%34
100%0%0%24
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400058

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths3 yrs 5 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)Jun 2027Dec 2027
Concrete structure (RCC)100%62%
Units booked (free sale)92%27%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Mesacon Crown by Mesacon Spaces LLP is an 87-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in April 2024 with possession due in June 2027. 37 units booked out of 40 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mesacon Crown is a BMC-sanctioned project by Mesacon Spaces LLP in Andheri West, Mumbai 400058, registered with MahaRERA as P51800055536. It was launched in April 2024. It has 87 units in 2 buildings: 85 homes (1, 2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 87 units, 40 are for sale and 47 are rehab units for existing members.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 18% complete.

37 units booked out of 40 units for sale (92%). Since the July 2026 update, 3 more units have been booked.