Vasant Heritage, Borivali East

by Pratham Developers · Borivali East, Mumbai 400066 · Map

Launched
Apr 20241 yr 8 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
66%Mid-construction
Booked (free sale)
13 of 1872% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 18 units

Rehab14 units for existing members

Total 32 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
1
2 BHK
11
3 BHK
18
Total units
32
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
18
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)66%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 66%Oct 2026: Concrete structure (RCC) 66%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 66%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%66%0%13
100%66%0%13
100%0%0%7
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400066

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 8 mths3 yrs
Possession date extendedBy 1 yr1 of 4
Possession date (MahaRERA)Dec 2026Nov 2027
Concrete structure (RCC)66%70%
Units booked (free sale)72%65%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Vasant Heritage by Pratham Developers is a 32-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in April 2024 with possession due in December 2026. 13 units booked out of 18 units for sale. The concrete structure (RCC) is 66% complete.

Read full summary

Vasant Heritage is a BMC-sanctioned project by Pratham Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800055545. It was launched in April 2024. It has 32 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 32 units, 18 are for sale and 14 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 66% complete, final finishes not started.

13 units booked out of 18 units for sale (72%).