Adinath Heights, Borivali East

Ready to moveLapsed

by M/S Shri Neelkanth Developers · Borivali East, Mumbai 400066 · Map

Launched
Feb 20242 yrs 1 mth promised
Possession (MahaRERA)
Mar 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
13 of 2065% · 8 in Jul 2026
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
2 BHK
14
3 BHK
3
4 BHK
1
Total units
20
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%13
100%100%100%8
100%100%0%8
100%100%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400066

Projects with 10–40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 1 mth1 yr 9 mths
Possession date extendedNo3 of 4
Possession date (MahaRERA)Mar 2026Feb 2027
Concrete structure (RCC)100%83%
Units booked65%76%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Adinath Heights by M/S Shri Neelkanth Developers is a 20-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in February 2024; its MahaRERA registration has lapsed. 13 units booked out of total 20 units. The concrete structure (RCC) is complete.

Read full summary

Adinath Heights is a BMC-sanctioned project by M/S Shri Neelkanth Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800055072. It was launched in February 2024. It has 20 units in 1 building, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in March 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

13 units booked out of total 20 units (65%). Since the July 2026 update, 5 more units have been booked.