Kannamwar Nagar Gurukul Co-Op. Hsg. Soc. Ltd, Vikhroli
by Kannamwar Nagar Gurukul Co Op Hsg Soc Ltd · Vikhroli, Mumbai 400083 · Map
- Launched
- Apr 20243 yrs 1 mth promised
- Possession (MahaRERA)
- May 2027Not extended
- Concrete structure
- 55%Mid-construction
- Booked (free sale)
- 33 of 6849% · 20 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 68 units
Rehab20 units for existing members
Total 88 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 36
- 3 BHK
- 20
- Other units
- 12
- Total units
- 88
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 68
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 55% | 0% | 33 | |
| 100% | 10% | 0% | 32 | |
| 100% | 0% | 0% | 24 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 3 yrs 4 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | May 2027 | Mar 2028 |
| Concrete structure (RCC) | 55% | 4% |
| Units booked (free sale) | 49% | 23% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- MK Emerald, Vikhroli
- Yash Pratik, Vikhroli
- Shree, Vikhroli
- Unique Platinum, Vikhroli
- Unique Grooves, Vikhroli
- Kannamwar Nagar Panchsheel CHSL, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| MK Emerald | April 2024 | August 2027 | 72% | 88 units booked out of 96 units for sale |
| Yash Pratik | February 2024 | December 2028 | 0% | – |
| Shree | June 2024 | December 2028 | 82% | 3 units booked out of 58 units for sale |
| Unique Platinum | July 2024 | November 2027 | 0% | 22 units booked out of total 58 units |
| Unique Grooves | July 2024 | September 2027 | 4% | 28 units booked out of total 123 units |
| Kannamwar Nagar Panchsheel CHSL | January 2024 | June 2028 | 5% | 0 units booked out of 111 units for sale |
About this project
Kannamwar Nagar Gurukul Co-Op. Hsg. Soc. Ltd by Kannamwar Nagar Gurukul Co Op Hsg Soc Ltd is an 88-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in April 2024 with possession due in May 2027. 33 units booked out of 68 units for sale. The concrete structure (RCC) is 55% complete.
Read full summary
Kannamwar Nagar Gurukul Co-Op. Hsg. Soc. Ltd is a MHADA-sanctioned project by Kannamwar Nagar Gurukul Co Op Hsg Soc Ltd in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800055601. It was launched in April 2024. It has 88 units in 1 building: 76 homes (1, 2 and 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 68 are for sale and 20 are rehab units for existing members.
Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.
33 units booked out of 68 units for sale (49%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 10% to 55%.