Skip to main content

MK Emerald, Vikhroli

by Matrix Constructions · Vikhroli, Mumbai 400083 · Map

Launched
Apr 20243 yrs 4 mths promised
Possession (MahaRERA)
Aug 2027Not extended
Concrete structure
72%Mid-construction
Booked (free sale)
88 of 9692% · 16 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale88 booked out of 96 units

Rehab16 units for existing members

Total 112 units. Rehab units are not for sale.

Project facts

1 BHK
84
2 BHK
22
Other units
6
Total units
112
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
96
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 72%Oct 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 72%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%0%88
100%72%0%88
100%72%0%81
100%0%0%38

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400083

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs 6 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Aug 2027Mar 2028
Concrete structure (RCC)72%30%
Units booked (free sale)92%23%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

MK Emerald by Matrix Constructions is a 112-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in April 2024 with possession due in August 2027. 88 units booked out of 96 units for sale. The concrete structure (RCC) is 72% complete.

Read full summary

MK Emerald is a MHADA-sanctioned project by Matrix Constructions in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800055884. It was launched in April 2024. It has 112 units in 1 building: 106 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 112 units, 96 are for sale and 16 are rehab units for existing members.

Its registered possession date is August 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 72% complete, final finishes not started.

88 units booked out of 96 units for sale (92%).