Shree, Vikhroli

by Jyd Infra Pvt Ltd · Vikhroli, Mumbai 400083 · Map

Launched
Jun 20244 yrs 6 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
82%Mid-construction
Booked (free sale)
3 of 585%
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 58 units

Land-owner share32 units, not for sale

Total 90 units. Land-owner units are not for sale.

Project facts

1 BHK
37
2 BHK
53
Total units
90
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
58
Land-owner share (not for sale)
32

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)82%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 1%Jul 2026: Concrete structure (RCC) 48%Oct 2026: Concrete structure (RCC) 82%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 82%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%82%0%3
100%48%0%1
100%1%0%1
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400083

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400083
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 3 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028Oct 2027
Concrete structure (RCC)82%4%
Units booked (free sale)5%38%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shree by Jyd Infra Pvt Ltd is a 90-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in June 2024 with possession due in December 2028. 3 units booked out of 58 units for sale. The concrete structure (RCC) is 82% complete.

Read full summary

Shree is a MHADA-sanctioned project by Jyd Infra Pvt Ltd in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800076595. It was launched in June 2024. It has 90 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 90 units, 58 are for sale and 32 are the land-owner's share, not for sale.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 82% complete, final finishes not started.

3 units booked out of 58 units for sale (5%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 48% to 82%.