Aim Heritage, Jogeshwari East

Ready to move

by M/s Aim Realtors Private Limited · Jogeshwari East, Mumbai 400060 · Map

Launched
Apr 20242 yrs 8 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
21 of 2584% · 10 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale21 booked out of 25 units

Rehab10 units for existing members

Total 35 units. Rehab units are not for sale.

Project facts

1 BHK
11
2 BHK
16
3 BHK
4
Other units
4
Total units
35
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
25
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 40%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%21
100%100%100%16
100%100%40%14
100%87%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400060

Projects with 10–70 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400060
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths4 yrs
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2026Dec 2028
Concrete structure (RCC)100%30%
Units booked (free sale)84%40%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Aim Heritage by M/s Aim Realtors Private Limited is a 35-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in April 2024 with possession due in December 2026. 21 units booked out of 25 units for sale. The concrete structure (RCC) is complete.

Read full summary

Aim Heritage is an SRA-sanctioned project by M/s Aim Realtors Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800055664. It was launched in April 2024. It has 35 units in 1 building: 31 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 25 are for sale and 10 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

21 units booked out of 25 units for sale (84%). Since the July 2026 update, 5 more units have been booked.