Regent Milan Chhaya, Jogeshwari East

by Regent Spaces · Jogeshwari East, Mumbai 400060 · Map

Launched
Feb 20254 yrs 1 mth promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
4 of 1040% · 16 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 10 units

Rehab16 units for existing members

Total 26 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
18
Total units
26
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
10
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%4
100%100%0%3
100%10%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400060

Projects with 10–60 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400060
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 1 mth3 yrs 6 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2029May 2028
Concrete structure (RCC)100%30%
Units booked (free sale)40%84%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Regent Milan Chhaya by Regent Spaces is a 26-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in February 2025 with possession due in March 2029. 4 units booked out of 10 units for sale. The concrete structure (RCC) is complete.

Read full summary

Regent Milan Chhaya is a BMC-sanctioned project by Regent Spaces in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800079327. It was launched in February 2025. It has 26 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 10 are for sale and 16 are rehab units for existing members.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

4 units booked out of 10 units for sale (40%). Since the July 2026 update, 1 more unit has been booked.