Kyrah Apartments, Jogeshwari East
by New Laxmi Enterprises · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Nov 20243 yrs 6 mths promised
- Possession (MahaRERA)
- May 2028Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 0 of 190% · 19 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 19 units
Rehab19 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 13
- 3 BHK
- 12
- 5+ BHK
- 1
- Total units
- 38
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 19
- Rehab units
- 19
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 0% | 0 | |
| 100% | 30% | 0% | 0 | |
| 100% | 0% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400060
Projects with 10–80 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 4 yrs |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | May 2028 | Dec 2028 |
| Concrete structure (RCC) | 30% | 100% |
| Units booked (free sale) | 0% | 84% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Avant Heritage - IV, Jogeshwari East
- Regent Milan Chhaya, Jogeshwari East
- Aim Heritage, Jogeshwari East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Avant Heritage - IV | December 2024 | December 2028 | 10% | 38 units booked out of total 38 units |
| Regent Milan Chhaya | February 2025 | March 2029 | 100% | 4 units booked out of 10 units for sale |
| Aim Heritage | April 2024 | December 2026 | 100% | 21 units booked out of 25 units for sale |
About this project
Kyrah Apartments by New Laxmi Enterprises is a 38-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in November 2024 with possession due in May 2028. 0 units booked out of 19 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Kyrah Apartments is a BMC-sanctioned project by New Laxmi Enterprises in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800078106. It was launched in November 2024. It has 38 units in 1 building, with 1, 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 19 are for sale and 19 are rehab units for existing members.
Its registered possession date is May 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.
0 units booked out of 19 units for sale (0%).