Meena House, Kandivali West
Ready to move
by Ramesh R Parekh Huf · Kandivali West, Mumbai 400067 · Map
- Launched
- Apr 20242 yrs 11 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 24 of 2983% · 7 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 29 units
Rehab7 units for existing members
Total 36 units. Rehab units are not for sale.
Project facts
- 1 RK
- 9
- 1 BHK
- 27
- Total units
- 36
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 29
- Rehab units
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 24 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 40% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400067
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 3 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2027 | Jun 2027 |
| Concrete structure (RCC) | 100% | 70% |
| Units booked (free sale) | 83% | 76% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Ambrose Heights, Kandivali West
- Sahakar Vatika, Kandivali West
- Pratap Mithila, Kandivali West
- Rodium - Xone, Kandivali West
- Swastik House - C Wing, Kandivali West
- Charkop Dr Ambedkar College Teachers Co Operative Housing Society Ltd, Kandivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ambrose Heights | May 2024 | March 2027 | 100% | 1 unit booked out of 16 units for sale |
| Sahakar Vatika | May 2024 | December 2027 | 100% | 51 units booked out of 52 units for sale |
| Pratap Mithila | June 2024 | June 2027 | 0% | 7 units booked out of 13 units for sale |
| Rodium - Xone | January 2024 | June 2027 | 17% | 76 units booked out of total 96 units |
| Swastik House - C Wing | August 2024 | March 2030 | 40% | – |
| Charkop Dr Ambedkar College Teachers Co Operative Housing Society Ltd | November 2023 | December 2026 | 100% | 32 units booked out of 42 units for sale |
About this project
Meena House by Ramesh R Parekh Huf is a 36-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in April 2024 with possession due in March 2027. 24 units booked out of 29 units for sale. The concrete structure (RCC) is complete.
Read full summary
Meena House is a BMC-sanctioned project by Ramesh R Parekh Huf in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800055787. It was launched in April 2024. It has 36 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 29 are for sale and 7 are rehab units for existing members.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
24 units booked out of 29 units for sale (83%).