Ambrose Heights, Kandivali West

by Dadamiya Infrastructure LLP · Kandivali West, Mumbai 400067 · Map

Launched
May 20242 yrs 10 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
1 of 166% · 20 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 16 units

Rehab20 units for existing members

Total 36 units. Rehab units are not for sale.

Project facts

1 BHK
18
2 BHK
14
Other units
4
Total units
36
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%1
100%100%0%1
100%90%0%1
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths3 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2027Sep 2027
Concrete structure (RCC)100%70%
Units booked (free sale)6%90%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ambrose Heights by Dadamiya Infrastructure LLP is a 36-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in May 2024 with possession due in March 2027. 1 unit booked out of 16 units for sale. The concrete structure (RCC) is complete.

Read full summary

Ambrose Heights is a BMC-sanctioned project by Dadamiya Infrastructure LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800056407. It was launched in May 2024. It has 36 units in 1 building: 32 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 16 are for sale and 20 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

1 unit booked out of 16 units for sale (6%).