Skip to main content

Pratap Mithila, Kandivali West

by JPV Realtors Private Limited · Kandivali West, Mumbai 400067 · Map

Launched
Jun 20243 yrs promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
7 of 1354% · 23 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 13 units

Rehab23 units for existing members

Total 36 units. Rehab units are not for sale.

Project facts

1 BHK
20
2 BHK
16
Total units
36
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
23

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%7
100%0%0%–
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400067

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2027Jul 2027
Concrete structure (RCC)0%100%
Units booked (free sale)54%90%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pratap Mithila by JPV Realtors Private Limited is a 36-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in June 2024 with possession due in June 2027. 7 units booked out of 13 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Pratap Mithila is a BMC-sanctioned project by JPV Realtors Private Limited in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800076713. It was launched in June 2024. It has 36 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 13 are for sale and 23 are rehab units for existing members.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

7 units booked out of 13 units for sale (54%).