Sayba Tulip, Kurla East

Ready to move

by Star Raise · Kurla East, Mumbai 400024 · Map

Launched
Jun 20242 yrs 9 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
110 of 11992% · 20 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale110 booked out of 119 units

Rehab20 units for existing members

Total 139 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
117
3 BHK
21
Total units
139
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
119
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 15%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 85%Jul 2026: Final finishes 95%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%110
100%100%95%95
100%100%85%65
100%15%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400024

Projects with 60–300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400024
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 9 mths2 yrs 10 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2027May 2027
Concrete structure (RCC)100%95%
Units booked (free sale)92%60%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Sayba Tulip by Star Raise is a 139-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in June 2024 with possession due in March 2027. 110 units booked out of 119 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sayba Tulip is a MHADA-sanctioned project by Star Raise in Kurla East, Mumbai 400024, registered with MahaRERA as P51800076688. It was launched in June 2024. It has 139 units in 1 building, with 1 RK, 1 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 139 units, 119 are for sale and 20 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

110 units booked out of 119 units for sale (92%). Since the July 2026 update, 15 more units have been booked.