Mirchandani Gold Stone, Bandra West
by Palms Sky Housing Private Limtied · Bandra West, Mumbai 400050 · Map
- Launched
- May 20242 yrs 10 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 4 of 850%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 8 units
Land-owner share13 units, not for sale
Total 21 units. Land-owner units are not for sale.
Project facts
- 3 BHK
- 9
- 4 BHK
- 9
- Other units
- 3
- Total units
- 21
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 8
- Land-owner share (not for sale)
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 4 | |
| 100% | 26% | 0% | 4 | |
| 100% | 26% | 0% | – | |
| 100% | 26% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400050
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 11 mths |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | Mar 2027 | Oct 2028 |
| Concrete structure (RCC) | 100% | 70% |
| Units booked (free sale) | 50% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Supreme Prana, Bandra West
- Santa Ritta, Bandra West
- Bellissima, Bandra West
- The Panorama By Rustomjee, Bandra West
- Verdant, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Supreme Prana | May 2024 | April 2028 | 63% | 5 units booked out of 5 units for sale |
| Santa Ritta | June 2024 | December 2027 | 100% | 6 units booked out of 9 units for sale |
| Bellissima | June 2024 | December 2028 | 60% | 17 units booked out of total 33 units |
| The Panorama By Rustomjee | February 2024 | October 2028 | 100% | 11 units booked out of 14 units for sale |
| Verdant | January 2024 | October 2029 | 70% | 0 units booked out of total 39 units |
About this project
Mirchandani Gold Stone by Palms Sky Housing Private Limtied is a 21-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in May 2024 with possession due in March 2027. 4 units booked out of 8 units for sale. The concrete structure (RCC) is complete.
Read full summary
Mirchandani Gold Stone is a BMC-sanctioned project by Palms Sky Housing Private Limtied in Bandra West, Mumbai 400050, registered with MahaRERA as P51800056099. It was launched in May 2024. It has 21 units in 1 building: 18 homes (3 and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 8 are for sale and 13 are the land-owner's share, not for sale.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
4 units booked out of 8 units for sale (50%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 26% to 100%.