Santa Ritta, Bandra West
by Paramount Builders · Bandra West, Mumbai 400050 · Map
- Launched
- Jun 20242 yrs originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 1 yr 6 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 6 of 967% · 14 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 9 units
Rehab14 units for existing members
Total 23 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 3 BHK
- 17
- 4 BHK
- 4
- Other units
- 1
- Total units
- 23
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 9
- Rehab units
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 6 | |
| 100% | 100% | 60% | 6 | |
| 50% | 0% | 0% | 0 | |
| 50% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400050
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs | 3 yrs 8 mths |
| Possession date extended | By 1 yr 6 mths | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Feb 2028 |
| Concrete structure (RCC) | 100% | 82% |
| Units booked (free sale) | 67% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Bellissima, Bandra West
- Supreme Prana, Bandra West
- Mirchandani Gold Stone, Bandra West
- Vaswani Avania, Bandra West
- Hill View, Bandra West
- The Panorama By Rustomjee, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bellissima | June 2024 | December 2028 | 60% | 17 units booked out of total 33 units |
| Supreme Prana | May 2024 | April 2028 | 63% | 5 units booked out of 5 units for sale |
| Mirchandani Gold Stone | May 2024 | March 2027 | 100% | 4 units booked out of 8 units for sale |
| Vaswani Avania | July 2024 | December 2027 | 100% | 13 units booked out of 16 units for sale |
| Hill View | October 2024 | December 2026 | 0% | 6 units booked out of 11 units for sale |
| The Panorama By Rustomjee | February 2024 | October 2028 | 100% | 11 units booked out of 14 units for sale |
About this project
Santa Ritta by Paramount Builders is a 23-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in June 2024 with possession due in December 2027. 6 units booked out of 9 units for sale. The concrete structure (RCC) is complete.
Read full summary
Santa Ritta is a BMC-sanctioned project by Paramount Builders in Bandra West, Mumbai 400050, registered with MahaRERA as P51800076838. It was launched in June 2024. It has 23 units in 1 building: 22 homes (1, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 9 are for sale and 14 are rehab units for existing members.
Its registered possession date is December 2027, extended by 1 year 6 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
6 units booked out of 9 units for sale (67%).