The Panorama By Rustomjee, Bandra West

by Keyorbit Realtors Private Limited · Bandra West, Mumbai 400050 · Map

Launched
Feb 20244 yrs 8 mths promised
Possession (MahaRERA)
Oct 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
11 of 1479% · 10 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 14 units

Rehab10 units for existing members

Total 24 units. Rehab units are not for sale.

Project facts

4 BHK
21
5+ BHK
3
Total units
24
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services6%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 38%Dec 2025: Excavation 38%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 6%Excavation 100%Concrete structure (RCC) 100%Final finishes 6%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%6%11
100%100%0%11
38%0%0%10
38%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 8 mths2 yrs 11 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Oct 2028Feb 2028
Concrete structure (RCC)100%85%
Units booked (free sale)79%55%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

The Panorama By Rustomjee by Keyorbit Realtors Private Limited (Rustomjee) is a 24-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in February 2024 with possession due in October 2028. 11 units booked out of 14 units for sale. The concrete structure (RCC) is complete.

Read full summary

The Panorama By Rustomjee is an SRA-sanctioned project by Keyorbit Realtors Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as P51800054920. It was launched in February 2024. It has 24 units in 1 building, with 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 14 are for sale and 10 are rehab units for existing members.

Its registered possession date is October 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 6% complete.

11 units booked out of 14 units for sale (79%).

Rustomjee's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA38
Total units across these projects3,435
Completed without extending the possession date15
Completed after an extension2
Lapsed5
Under construction16
Possession date extended on the builder's application8
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Rustomjee projects119 (11 of 38 projects)