Skip to main content

Park Grandezza, Andheri West

by Shree Mahavir Estates · Andheri West, Mumbai 400053 · Map

Launched
Jun 20249 yrs 8 mths promised
Possession (MahaRERA)
Feb 2034Not extended
Concrete structure
15%Mid-construction
Booked (free sale)
34 of 10034% · 40 rehab units
Buildings
30.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale34 booked out of 100 units

Rehab40 units for existing members

Total 140 units. Rehab units are not for sale.

Project facts

3 BHK
140
Total units
140
Buildings
3
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
100
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)15%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 15%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 15%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%34
100%0%0%33
100%0%0%33
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400053

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)9 yrs 8 mths4 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Feb 2034Jul 2029
Concrete structure (RCC)15%89%
Units booked (free sale)34%74%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Park Grandezza by Shree Mahavir Estates is a 140-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in June 2024 with possession due in February 2034. 34 units booked out of 100 units for sale. The concrete structure (RCC) is 15% complete.

Read full summary

Park Grandezza is a MHADA-sanctioned project by Shree Mahavir Estates in Andheri West, Mumbai 400053, registered with MahaRERA as P51800066462. It was launched in June 2024. It has 140 units in 3 buildings, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 140 units, 100 are for sale and 40 are rehab units for existing members.

Its registered possession date is February 2034, unchanged since launch. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.

34 units booked out of 100 units for sale (34%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 0% to 15%.