Bharat Auravistas, Andheri West

by Bharat Realty Venture Private Limited · Andheri West, Mumbai 400053 · Map

Launched
Aug 20244 yrs 11 mths promised
Possession (MahaRERA)
Jul 2029Not extended
Concrete structure
89%Mid-construction
Booked (free sale)
87 of 11377% · 70 rehab units
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale87 booked out of 113 units

Rehab70 units for existing members

Total 183 units. Rehab units are not for sale.

Project facts

2 BHK
30
3 BHK
143
Other units
10
Total units
183
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
113
Rehab units
70

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)89%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 5%Jul 2026: Concrete structure (RCC) 56%Oct 2026: Concrete structure (RCC) 89%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 89%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%89%0%87
100%56%0%85
100%5%0%66
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400053

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths4 yrs 8 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Jul 2029Jul 2029
Concrete structure (RCC)89%49%
Units booked (free sale)77%35%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Bharat Auravistas by Bharat Realty Venture Private Limited is a 183-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in August 2024 with possession due in July 2029. 87 units booked out of 113 units for sale. The concrete structure (RCC) is 89% complete.

Read full summary

Bharat Auravistas is a MHADA-sanctioned project by Bharat Realty Venture Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800077277. It was launched in August 2024. It has 183 units in 1 building: 173 homes (2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 183 units, 113 are for sale and 70 are rehab units for existing members.

Its registered possession date is July 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 89% complete, final finishes not started.

87 units booked out of 113 units for sale (77%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 56% to 89%.