Disha Elysium, Andheri West
by Disha Construction · Andheri West, Mumbai 400053 · Map
- Launched
- Nov 20245 yrs 4 mths promised
- Possession (MahaRERA)
- Mar 2030Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 19 of 5435% · 50 rehab units
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale19 booked out of 54 units
Rehab50 units for existing members
Total 104 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 73
- 3 BHK
- 31
- Total units
- 104
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 54
- Rehab units
- 50
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 0% | 19 | |
| 100% | 30% | 0% | 14 | |
| 100% | 30% | 0% | 10 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400053
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2030 | May 2029 |
| Concrete structure (RCC) | 30% | 32% |
| Units booked (free sale) | 35% | 39% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Azad Nagar Alfa Chs Ltd, Andheri West
- Gayatri Enclave, Andheri West
- Bharat Auravistas, Andheri West
- Swaroop Grandeur, Andheri West
- Platinum Crest, Andheri West
- Park Grandezza, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Azad Nagar Alfa Chs Ltd | January 2025 | December 2028 | 68% | 10 units booked out of 48 units for sale |
| Gayatri Enclave | February 2025 | December 2029 | 50% | 5 units booked out of 47 units for sale |
| Bharat Auravistas | August 2024 | July 2029 | 89% | 87 units booked out of 113 units for sale |
| Swaroop Grandeur | April 2025 | March 2029 | 6% | 32 units booked out of 56 units for sale |
| Platinum Crest | April 2025 | December 2028 | 0% | 38 units booked out of 88 units for sale |
| Park Grandezza | June 2024 | February 2034 | 15% | 34 units booked out of 100 units for sale |
About this project
Disha Elysium by Disha Construction is a 104-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in November 2024 with possession due in March 2030. 19 units booked out of 54 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Disha Elysium is a BMC-sanctioned project by Disha Construction in Andheri West, Mumbai 400053, registered with MahaRERA as P51800077977. It was launched in November 2024. It has 104 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 104 units, 54 are for sale and 50 are rehab units for existing members.
Its registered possession date is March 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.
19 units booked out of 54 units for sale (35%). Since the July 2026 update, 5 more units have been booked.