Nanak Niwas, Santacruz West

Ready to move

by Roodraksh Probuilder And Infracon Pvt Ltd · Santacruz West, Mumbai 400054 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
1 of 714%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 7 units

Land-owner share13 units, not for sale

Total 20 units. Land-owner units are not for sale.

Project facts

3 BHK
14
4 BHK
3
5+ BHK
3
Total units
20
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
7
Land-owner share (not for sale)
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 6%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%1
100%100%90%1
100%90%10%1
100%6%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027May 2027
Concrete structure (RCC)100%90%
Units booked (free sale)14%62%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Nanak Niwas by Roodraksh Probuilder And Infracon Pvt Ltd is a 20-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in June 2024 with possession due in December 2027. 1 unit booked out of 7 units for sale. The concrete structure (RCC) is complete.

Read full summary

Nanak Niwas is a BMC-sanctioned project by Roodraksh Probuilder And Infracon Pvt Ltd in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800066496. It was launched in June 2024. It has 20 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 7 are for sale and 13 are the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

1 unit booked out of 7 units for sale (14%).