by Ummang Lifespaces LLP · Santacruz West, Mumbai 400054 · Map

Launched
Jun 20243 yrs 6 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
81%Mid-construction
Booked (free sale)
3 of 560% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 5 units

Rehab14 units for existing members

Total 19 units. Rehab units are not for sale.

Project facts

3 BHK
18
4 BHK
1
Total units
19
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
5
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)81%
Finishes, lifts and services2%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 14%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 81%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 2%Oct 2026: Final finishes 2%Excavation 100%Concrete structure (RCC) 81%Final finishes 2%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%81%2%3
100%92%2%2
100%78%0%2
100%14%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400054

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths3 yrs
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2027May 2027
Concrete structure (RCC)81%100%
Units booked (free sale)60%43%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Sunbeam by Ummang Lifespaces LLP is a 19-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in June 2024 with possession due in December 2027. 3 units booked out of 5 units for sale. The concrete structure (RCC) is 81% complete.

Read full summary

Sunbeam is a BMC-sanctioned project by Ummang Lifespaces LLP in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800076799. It was launched in June 2024. It has 19 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 19 units, 5 are for sale and 14 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 81% complete, final finishes 2% complete.

3 units booked out of 5 units for sale (60%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 92% to 81%.