by Aum Serenity · Santacruz West, Mumbai 400054 · Map

Launched
May 20243 yrs promised
Possession (MahaRERA)
May 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
12 of 1486% · 24 rehab units
Buildings
30.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale12 booked out of 14 units

Rehab24 units for existing members

Total 38 units. Rehab units are not for sale.

Project facts

3 BHK
24
4 BHK
13
Other units
1
Total units
38
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services47%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 92%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 47%Oct 2026: Final finishes 47%Excavation 100%Concrete structure (RCC) 100%Final finishes 47%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%47%12
100%100%47%12
100%92%0%11
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400054

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400054
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 4 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)May 2027Dec 2027
Concrete structure (RCC)100%90%
Units booked (free sale)86%60%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Amara by Aum Serenity is a 38-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in May 2024 with possession due in May 2027. 12 units booked out of 14 units for sale. The concrete structure (RCC) is complete.

Read full summary

Amara is a BMC-sanctioned project by Aum Serenity in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800056369. It was launched in May 2024. It has 38 units in 3 buildings: 37 homes (3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 14 are for sale and 24 are rehab units for existing members.

Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 47% complete.

12 units booked out of 14 units for sale (86%).