Sayba Royal, Kurla East
by M/S. Star Rise · Kurla East, Mumbai 400024 · Map
- Launched
- Jan 20251 yr 11 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 44 of 11239% · 40 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale44 booked out of 112 units
Rehab40 units for existing members
Total 152 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 52
- 2 BHK
- 92
- 5+ BHK
- 1
- Other units
- 7
- Total units
- 152
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 112
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 44 | |
| 100% | 75% | 0% | 44 | |
| 100% | 35% | 0% | 44 | |
| 90% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400024
Projects with 70–300 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 11 mths | 2 yrs 9 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Dec 2026 | May 2027 |
| Concrete structure (RCC) | 95% | 100% |
| Units booked (free sale) | 39% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Sayba Crystal, Kurla East
- Sayba Tulip, Kurla East
- Sayba Swarna, Kurla East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sayba Crystal | July 2024 | May 2027 | 100% | 131 units booked out of 145 units for sale |
| Sayba Tulip | June 2024 | March 2027 | 100% | 110 units booked out of 119 units for sale |
| Sayba Swarna | September 2025 | December 2027 | 20% | 80 units booked out of 115 units for sale |
About this project
Sayba Royal by M/S. Star Rise is a 152-unit MHADA-sanctioned project in Kurla East, Mumbai 400024, launched in January 2025 with possession due in December 2026. 44 units booked out of 112 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Sayba Royal is a MHADA-sanctioned project by M/S. Star Rise in Kurla East, Mumbai 400024, registered with MahaRERA as P51800078687. It was launched in January 2025. It has 152 units in 2 buildings: 145 homes (1, 2 and 5+ BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 152 units, 112 are for sale and 40 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
44 units booked out of 112 units for sale (39%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 75% to 95%.