Dollars Avenue CHSL, Borivali West
by M/S Hirani Realtors · Borivali West, Mumbai 400092 · Map
- Launched
- Jun 20243 yrs 5 mths promised
- Possession (MahaRERA)
- Nov 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 6 of 1932% · 28 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 19 units
Rehab28 units for existing members
Total 47 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 15
- 2 BHK
- 8
- 3 BHK
- 10
- Other units
- 14
- Total units
- 47
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 19
- Rehab units
- 28
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 6 | |
| 100% | 60% | 0% | 3 | |
| 100% | 58% | 0% | 4 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400092
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 3 yrs 8 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Nov 2027 | Jan 2028 |
| Concrete structure (RCC) | 100% | 86% |
| Units booked (free sale) | 32% | 56% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Gautam Prabhu, Borivali West
- Darshan Tower Chs Redevelopment Project, Borivali West
- Shree Radhe Shyam Heights, Borivali West
- Om Amar Shakti, Borivali West
- Anmol Residency, Borivali West
- Jalaram Enclave, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Gautam Prabhu | May 2024 | April 2027 | 100% | 4 units booked out of 6 units for sale |
| Darshan Tower Chs Redevelopment Project | July 2024 | March 2028 | 95% | 29 units booked out of 37 units for sale |
| Shree Radhe Shyam Heights | April 2024 | December 2027 | 100% | 14 units booked out of 22 units for sale |
| Om Amar Shakti | April 2024 | April 2028 | 76% | 7 units booked out of 35 units for sale |
| Anmol Residency | February 2024 | December 2028 | 20% | 4 units booked out of total 20 units |
| Jalaram Enclave | October 2024 | June 2027 | 0% | 23 units booked out of 48 units for sale |
About this project
Dollars Avenue CHSL by M/S Hirani Realtors is a 47-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in June 2024 with possession due in November 2027. 6 units booked out of 19 units for sale. The concrete structure (RCC) is complete.
Read full summary
Dollars Avenue CHSL is a BMC-sanctioned project by M/S Hirani Realtors in Borivali West, Mumbai 400092, registered with MahaRERA as P51800076786. It was launched in June 2024. It has 47 units in 1 building: 33 homes (1, 2 and 3 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 19 are for sale and 28 are rehab units for existing members.
Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
6 units booked out of 19 units for sale (32%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 100%.