Jalaram Enclave, Borivali West

by Shree Sundha Developers · Borivali West, Mumbai 400092 · Map

Launched
Oct 20242 yrs 8 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
23 of 4848% · 44 rehab units
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale23 booked out of 48 units

Rehab44 units for existing members

Total 92 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
29
3 BHK
36
4 BHK
1
Other units
22
Total units
92
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Free-sale units
48
Rehab units
44

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%23
100%0%0%18
100%0%0%5
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400092

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 8 mths4 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2027Jun 2028
Concrete structure (RCC)0%98%
Units booked (free sale)48%54%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Jalaram Enclave by Shree Sundha Developers is a 92-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in October 2024 with possession due in June 2027. 23 units booked out of 48 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Jalaram Enclave is an SRA-sanctioned project by Shree Sundha Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800077587. It was launched in October 2024. It has 92 units in 1 building: 70 homes (1, 2, 3 and 4 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 92 units, 48 are for sale and 44 are rehab units for existing members.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

23 units booked out of 48 units for sale (48%). Since the July 2026 update, 5 more units have been booked.