Sumit KMR Param, Borivali West
by Sumit Woods Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Jun 20244 yrs 9 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 50%Mid-construction
- Booked
- 172 of 22277% · 136 in Jul 2026
- Buildings
- 11.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 168
- 3 BHK
- 54
- Total units
- 222
- Buildings
- 1
- Land
- 1.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | 172 | |
| 100% | 50% | 0% | 136 | |
| 100% | 25% | 0% | 57 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400092
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 9 mths | 4 yrs 11 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Mar 2029 | Mar 2029 |
| Concrete structure (RCC) | 50% | 13% |
| Units booked | 77% | 74% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Unique Regalia, Borivali West
- Altus, Borivali West
- Inspira Aura, Borivali West
- Dotom Hilton, Borivali West
- Nicco Vanashri And Nicco Heights, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Unique Regalia | July 2024 | June 2029 | 0% | 54 units booked out of 70 units for sale |
| Altus | August 2024 | December 2030 | 29% | 169 units booked out of total 204 units |
| Inspira Aura | February 2024 | March 2029 | 13% | 87 units booked out of 124 units for sale |
| Dotom Hilton | February 2024 | August 2027 | 0% | – |
| Nicco Vanashri And Nicco Heights | November 2024 | December 2028 | 53% | 102 units booked out of 215 units for sale |
About this project
Sumit KMR Param by Sumit Woods Limited is a 222-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in June 2024 with possession due in March 2029. 172 units booked out of total 222 units. The concrete structure (RCC) is 50% complete.
Read full summary
Sumit KMR Param is a BMC-sanctioned project by Sumit Woods Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800076840. It was launched in June 2024. It has 222 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.
172 units booked out of total 222 units (77%). Since the July 2026 update, 36 more units have been booked.