Unique Regalia, Borivali West
by Unique Shanti Developers LLP · Borivali West, Mumbai 400092 · Map
- Launched
- Jul 20244 yrs 11 mths promised
- Possession (MahaRERA)
- Jun 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 54 of 7077%
- Buildings
- 31.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale54 booked out of 70 units
Land-owner share276 units, not for sale
Total 346 units. Land-owner units are not for sale.
Project facts
- 1 RK
- 153
- 2 BHK
- 113
- 3 BHK
- 27
- Other units
- 53
- Total units
- 346
- Buildings
- 3
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 70
- Land-owner share (not for sale)
- 276
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 54 | |
| 100% | 0% | 0% | 51 | |
| 100% | 0% | 0% | 46 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400092
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 11 mths | 4 yrs 9 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Jun 2029 | Mar 2029 |
| Concrete structure (RCC) | 0% | 29% |
| Units booked (free sale) | 77% | 74% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- Sumit KMR Param, Borivali West
- Altus, Borivali West
- Nicco Vanashri And Nicco Heights, Borivali West
- Inspira Aura, Borivali West
- Dotom Hilton, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sumit KMR Param | June 2024 | March 2029 | 50% | 172 units booked out of total 222 units |
| Altus | August 2024 | December 2030 | 29% | 169 units booked out of total 204 units |
| Nicco Vanashri And Nicco Heights | November 2024 | December 2028 | 53% | 102 units booked out of 215 units for sale |
| Inspira Aura | February 2024 | March 2029 | 13% | 87 units booked out of 124 units for sale |
| Dotom Hilton | February 2024 | August 2027 | 0% | – |
About this project
Unique Regalia by Unique Shanti Developers LLP is a 346-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in July 2024 with possession due in June 2029. 54 units booked out of 70 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Unique Regalia is an SRA-sanctioned project by Unique Shanti Developers LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800076881. It was launched in July 2024. It has 346 units in 3 buildings: 293 homes (1 RK, 2 BHK and 3 BHK) and 53 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 346 units, 70 are for sale and 276 are the land-owner's share, not for sale.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.
54 units booked out of 70 units for sale (77%). Since the July 2026 update, 3 more units have been booked.