Altus, Borivali West
by Lodha Developers Limited · Borivali West, Mumbai 400092 · Map
- Launched
- Aug 20245 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2030Extended by 1 yr
- Concrete structure
- 29%Mid-construction
- Booked
- 169 of 20483% · 163 in Jul 2026
- Buildings
- 11.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 121
- 4 BHK
- 77
- 5+ BHK
- 6
- Total units
- 204
- Buildings
- 1
- Land
- 1.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 29% | 0% | 169 | |
| 100% | 14% | 0% | 163 | |
| 100% | 0% | 0% | 135 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400092
Projects with 100–450 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 4 yrs 9 mths |
| Possession date extended | By 1 yr | 0 of 5 |
| Possession date (MahaRERA) | Dec 2030 | Mar 2029 |
| Concrete structure (RCC) | 29% | 50% |
| Units booked | 83% | 77% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Unique Regalia, Borivali West
- Sumit KMR Param, Borivali West
- Nicco Vanashri And Nicco Heights, Borivali West
- Inspira Aura, Borivali West
- Ruparel Zinnia, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Unique Regalia | July 2024 | June 2029 | 0% | 54 units booked out of 70 units for sale |
| Sumit KMR Param | June 2024 | March 2029 | 50% | 172 units booked out of total 222 units |
| Nicco Vanashri And Nicco Heights | November 2024 | December 2028 | 53% | 102 units booked out of 215 units for sale |
| Inspira Aura | February 2024 | March 2029 | 13% | 87 units booked out of 124 units for sale |
| Ruparel Zinnia | February 2025 | June 2028 | 81% | 108 units booked out of total 133 units |
About this project
Altus by Lodha Developers Limited is a 204-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in August 2024 with possession due in December 2030. 169 units booked out of total 204 units. The concrete structure (RCC) is 29% complete.
Read full summary
Altus is a BMC-sanctioned project by Lodha Developers Limited in Borivali West, Mumbai 400092, registered with MahaRERA as P51800077358. It was launched in August 2024. It has 204 units in 1 building, with 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2030, extended by 1 year from the original December 2029. Construction: excavation complete, structure (RCC) 29% complete, final finishes not started.
169 units booked out of total 204 units (83%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 14% to 29%.
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.