Ariha Vincere, Goregaon West
by Velstand Realty LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- Jul 20242 yrs 11 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 48 of 5784% · 38 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale48 booked out of 57 units
Rehab38 units for existing members
Total 95 units. Rehab units are not for sale.
Project facts
- 1 RK
- 6
- 1 BHK
- 28
- 2 BHK
- 51
- Other units
- 10
- Total units
- 95
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 57
- Rehab units
- 38
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 48 | |
| 100% | 0% | 0% | 16 | |
| 100% | 0% | 0% | 16 | |
| 100% | 0% | 0% | 11 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400104
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2027 | Dec 2027 |
| Concrete structure (RCC) | 100% | 70% |
| Units booked (free sale) | 84% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Rivaan, Goregaon West
- Redevelopment Of Om Manikanta Chsl, Goregaon West
- Building No.9 - Phase II, Goregaon West
- Vogue77, Goregaon West
- Sanghvi Crystal, Goregaon West
- Siddharth Nagar Nishad Chsl, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Rivaan | July 2024 | December 2028 | 85% | 71 units booked out of 77 units for sale |
| Redevelopment Of Om Manikanta Chsl | July 2024 | December 2027 | 70% | 29 units booked out of 43 units for sale |
| Building No.9 - Phase II | June 2024 | December 2026 | 70% | 0 units booked out of total 52 units |
| Vogue77 | May 2024 | December 2027 | 89% | 57 units booked out of total 79 units |
| Sanghvi Crystal | October 2024 | February 2028 | 0% | 10 units booked out of 26 units for sale |
| Siddharth Nagar Nishad Chsl | November 2024 | December 2026 | 0% | – |
About this project
Ariha Vincere by Velstand Realty LLP is a 95-unit SRA-sanctioned project in Goregaon West, Mumbai 400104, launched in July 2024 with possession due in June 2027. 48 units booked out of 57 units for sale. The concrete structure (RCC) is complete.
Read full summary
Ariha Vincere is an SRA-sanctioned project by Velstand Realty LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800076927. It was launched in July 2024. It has 95 units in 1 building: 85 homes (1 RK, 1 BHK and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 95 units, 57 are for sale and 38 are rehab units for existing members.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
48 units booked out of 57 units for sale (84%). Since the July 2026 update, 32 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.